Disputes Resolution
Dispute Resolution Services
The National Construction Council (NCC) has been facilitating dispute resolution within Tanzania's construction industry since 1982 through Alternative Dispute Resolution (ADR) mechanisms.
As part of this mandate, NCC registers and maintains a panel of qualified dispute resolution practitioners who assist parties in resolving disputes arising from construction contracts. Dispute resolution is conducted in accordance with NCC Rules and applicable laws.
The functions of NCC are provided under Section 4 of the National Construction Council Act, Cap. 162 (R.E. 2023). One of these functions is to facilitate the resolution of disputes arising from construction activities.
Dispute Resolution Services Offered
NCC use two Alternative Dispute Resolution mechanisms:
Adjudication
Adjudication is a fast-track dispute resolution process where an independent Adjudicator issues a professional decision. The decision is immediately binding on the parties until it is revised or overturned through an Arbitration Award.
Arbitration
Arbitration is a dispute resolution process conducted by an independent Arbitrator who renders a final and binding decision upon the parties.
Applicable Laws and Rules
Dispute resolution services are governed by:
- Arbitration Act, Cap. 15, R.E. 2023
- Arbitration (Rules of Procedure) Regulations, GN No.146 of 2021
- NCC Arbitration Rules, 2001
- NCC Adjudication Rules, 2017
Requirements for Filing a Dispute
Before filing a dispute with NCC, an applicant must ensure that:
- A valid construction contract exists.
- The contract contains an Adjudication or Arbitration clause.
- NCC has been designated as the Appointing Authority.
- The legal time limit for filing the dispute has not expired.
- Any contractual pre-dispute procedures have been completed.
Procedure for Filing a Dispute
The dispute resolution process involves the following steps:
- Submit a written Notice of Dispute to NCC.
- Pay the filing fee of TZS 300,000.
- NCC serves the notice upon the other party.
- The responding party submits its response.
- NCC provides the list of registered adjudicators/arbitrators.
- Parties jointly appoint a dispute resolver.
- NCC formally appoints the selected practitioner.
- Proceedings commence until a determination or award is issued.
To become a NCC Dispute Resolution Practitioner
Adjudicator
Applicants must:
- Submit an application to NCC.
- Hold professional qualifications in Engineering, Architecture or Quantity Surveying.
- Be registered with the relevant professional board.
- Possess at least five years of professional experience.
- Demonstrate adequate knowledge of the construction industry.
- Have attended and successfully completed NCC Adjudication Training.
Arbitrator
Applicants must:
- Hold Accreditation from the Ministry of Constitution and Legal Affairs.
- Submit an application to NCC.
- Hold professional qualifications in Engineering, Architecture, Quantity Surveying or Law.
- Be registered with the relevant professional body.
- Possess at least five years of relevant experience.
- Have knowledge of Arbitration, Adjudication, Mediation or other ADR mechanisms.
- Have attended NCC Arbitration Training.
Cost of Proceedings
Unless otherwise directed by the dispute resolver or agreed in the contract, the costs of the proceedings shall be shared equally by both parties.